The project was finished in September 2013 in cooperation with Solektra LTD and Solvis LTD. Three integrated solar power plants were built on production and business sites of Gumiimpex-GRP. Two plants with the capacity of 221 kW at the location Pavleka Miškine 64 c and one with the capacity of 999 kW in Free zoneVaraždin, which is the largest integrated solar power plant built in Croatia. All produced electricity will be delivered to the distribution network at a privileged price.

The solar power plant Gumiimpex with the capacity of 999 kW has an expected annual production of 1.113 MWh of ecologically clean electricity. Expected annual yield lies at about 1.125 kWh per kW of installed power. The power plant also has its ecological component and during 30 years of business, it will have 16.835 tons less CO2 emissions compared to electricity produced in classical power plants that run on fossil fuels.